Project Management Professional (PMP) Exam Practice – Question0271

A project manager is assigned to start the charter of an IT project and review the process inputs. However, the project manager realizes that the business case does not have adequate support.
What should the project manager do to resolve this situation?


A.
Notify the project sponsor.
B. Hire an external subject matter expert (SME).
C. Request that the business analysis team perform an evaluation.
D. Propose a review of the lessons learned in similar projects.

Correct Answer: A