After joining a project during its initiation phase, a project manager learns that two key stakeholders disagree on project priorities.
What should the project manager do?
A. Escalate the issue to the project sponsor.
B. Log a risk describing how these competing expectations will impact the project.
C. Conduct a stakeholder analysis to understand and align project expectations.
D. Ask team members for advice.