Project Management Professional (PMP) Exam Practice – Question0283 A project in which the scope, time, and cost of delivery are determined as early as possible is following a life cycle that is: A. Adaptive B. Predictive C. Incremental D. Iterative Show Answer Hide Answer Correct Answer: B Post navigation Project Management Professional (PMP) Exam Practice – Question0282Project Management Professional (PMP) Exam Practice – Question0284