Project Management Professional (PMP) Exam Practice – Question0285

The only Process Group that comprises processes that typically occur from the beginning to the end of the project life cycle is:


A.
Planning.
B. Executing,
C. Monitoring and Controlling.
D. Closing.

Correct Answer: A