Project Management Professional (PMP) Exam Practice – Question0289 The Plan Stakeholder Management process belongs to which Process Group? A. Executing B. Initiating C. Planning D. Monitoring and Controlling Show Answer Hide Answer Correct Answer: C Post navigation Project Management Professional (PMP) Exam Practice – Question0288Project Management Professional (PMP) Exam Practice – Question0290