Project Management Professional (PMP) Exam Practice – Question0294

The process of estimating the type and quantity of material, human resources, equipment, or supplies required to perform each activity is known as:


A.
Collect Requirements.
B. Conduct Procurements.
C. Estimate Activity Durations.
D. Estimate Activity Resources.

Correct Answer: D