Which item is a formal proposal to modify any document, deliverable, or baseline?
A. Change request
B. Requirements documentation
C. Scope baseline
D. Risk urgency assessment
A. Change request
B. Requirements documentation
C. Scope baseline
D. Risk urgency assessment