Which process involves defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive plan?


A.
Direct and Manage Project Work
B. Develop Project Management Plan
C. Plan Quality Management
D. Monitor and Control Project Work

Correct Answer: B