Project Management Professional (PMP) Exam Practice – Question0304

Inputs to the Plan Schedule Management process include:


A.
Organizational process assets and the project charter,
B. Enterprise environmental factors and schedule tools.
C. Time tables and Pareto diagrams.
D. Activity attributes and resource calendars.

Correct Answer: A