Project Management Professional (PMP) Exam Practice – Question0307

The planned work contained in the lowest level of work breakdown structure (WBS) components is known as:


A.
Work packages.
B. Accepted deliverables.
C. The WBS dictionary.
D. The scope baseline.

Correct Answer: A