Project Management Professional (PMP) Exam Practice – Question0311

Units of measure, level of precision, level of accuracy, control thresholds, and rules of performance measurement are examples of items that are established in the:


A.
Cost management plan.
B. Work performance information.
C. Quality management plan.
D. Work breakdown structure.

Correct Answer: A