Project Management Professional (PMP) Exam Practice – Question0323

Which items are components of a project management plan?


A.
Change management plan, process improvement plan, and scope management plan
B. Agreements, procurement management plan, and work performance information
C. Schedule management plan, project schedule, and resource calendars
D. Scope baseline, project statement of work, and requirements traceability matrix

Correct Answer: A