Project Management Professional (PMP) Exam Practice – Question0330

A project team attempts to produce a deliverable and finds that they have neither the expertise nor the time to complete the deliverable in a timely manner. This issue could have been avoided if they had created and followed a:


A.
risk management plan
B. human resource management plan
C. scope management plan
D. procurement management plan

Correct Answer: D