Project Management Professional (PMP) Exam Practice – Question0335 The lowest level normally depicted in a work breakdown structure (WBS) is called a/an: A. work package B. deliverable C. milestone D. activity Show Answer Hide Answer Correct Answer: A Post navigation Project Management Professional (PMP) Exam Practice – Question0334Project Management Professional (PMP) Exam Practice – Question0336