Project Management Professional (PMP) Exam Practice – Question0339

Outputs of the Control Communications process include:


A.
expert judgment and change requests.
B. work performance information and change requests.
C. organizational process asset updates and an issue log.
D. project management plan updates and an issue log.

Correct Answer: B