Project Management Professional (PMP) Exam Practice – Question0347

Funding limit reconciliation is a tool and technique of which Project Cost Management process?


A.
Estimate Costs
B. Control Costs
C. Plan Cost Management
D. Determine Budget

Correct Answer: D