The process of identifying and documenting the specific actions to be performed to produce the project deliverables is known as:
A. Define Activities.
B. Sequence Activities.
C. Define Scope.
D. Control Schedule.
A. Define Activities.
B. Sequence Activities.
C. Define Scope.
D. Control Schedule.