Project Management Professional (PMP) Exam Practice – Question0361

Which of the following is a tool and technique for Estimate Activity Durations?


A.
Parametric estimating
B. Monte Carlo analysis
C. Alternatives analysis
D. Bottom-up estimating

Correct Answer: A