Project Management Professional (PMP) Exam Practice – Question0374

Portfolio Management is management of:


A.
a project by dividing the project into more manageable sub-projects.
B. a project by utilizing a portfolio of general management skills such as planning, organizing, staffing, executing, and controlling.
C. all projects undertaken by a company.
D. a collection of projects that are grouped together to facilitate effective management and meet strategic business objectives.

Correct Answer: D