Project Management Professional (PMP) Exam Practice – Question0381

A work package has been scheduled to cost $1,000 to complete and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed. What is the cost variance?


A.
-700
B. -200
C. 200
D. 500
-700
B. -200
C. 200
D. 500

Correct Answer: A