Project Management Professional (PMP) Exam Practice – Question0388

The milestone list is an input to which process from the Planning Process Group?


A.
Define Activities
B. Estimate Activity Durations
C. Estimate Activity Resources
D. Sequence Activities

Correct Answer: D