Project Management Professional (PMP) Exam Practice – Question0391

Tools and techniques used for Plan Communications include the communication:


A.
requirements analysis, communication technology, communication models, and communication methods.
B. methods, stakeholder register, communication technology, and communication models.
C. requirements, communication technology, communication requirements analysis, and communication methods.
D. management plan, communication technology, communication models, and communication requirements analysis.

Correct Answer: A