Project Management Professional (PMP) Exam Practice – Question0392

Which of the following are outputs of Develop Project Team?


A.
Human resources plan changes and project staff assignment updates
B. Project management plan updates and enterprise environmental factor updates
C. Resource calendars and project management plan updates
D. Team performance assessments and enterprise environmental factor updates

Correct Answer: D