What is the responsibility of the project manager and the functional manager respectively?


A.
Oversight for an administrative area; a facet of the core business
B. Achieving the project objectives; providing management oversight for an administrative area
C. A facet of the core business; achieving the project objectives
D. Both are responsible for achieving the project objectives.

Correct Answer: B