Project Management Professional (PMP) Exam Practice – Question0397 Which can be used to determine whether a process is stable or has predictable performance? A. Matrix diagram B. Histogram C. Control chart D. Flowchart Show Answer Hide Answer Correct Answer: C Post navigation Project Management Professional (PMP) Exam Practice – Question0396Project Management Professional (PMP) Exam Practice – Question0398