Project Management Professional (PMP) Exam Practice – Question0404

"Tailoring" is defined as the:


A.
effort of addressing each process to determine which are appropriate and their appropriate degree of rigor.
B. act of creating a project team with the specialized skills required to produce a required product or service.
C. action taken to bring a defective or nonconforming component into compliance with requirements or specifications.
D. adjustment of the respective influences of time, cost, and quality in order to most efficiently achieve scope.

Correct Answer: A