Project Management Professional (PMP) Exam Practice – Question0406 Which is an output from Distribute Information? A. Earned value analysis B. Trend analysis C. Project records D. Performance reviews Show Answer Hide Answer Correct Answer: C Post navigation Project Management Professional (PMP) Exam Practice – Question0405Project Management Professional (PMP) Exam Practice – Question0407