What are the identified risks for doing excessive decomposition in a WBS?
A. Insufficient project funding and disqualification of sellers
B. Insufficient project funding and ineffective use of resources
C. Disqualification of sellers and non-productive management efforts
D. Non-productive management effort and inefficient use of resources
A. Insufficient project funding and disqualification of sellers
B. Insufficient project funding and ineffective use of resources
C. Disqualification of sellers and non-productive management efforts
D. Non-productive management effort and inefficient use of resources