Project Management Professional (PMP) Exam Practice – Question0407

What are the identified risks for doing excessive decomposition in a WBS?


A.
Insufficient project funding and disqualification of sellers
B. Insufficient project funding and ineffective use of resources
C. Disqualification of sellers and non-productive management efforts
D. Non-productive management effort and inefficient use of resources

Correct Answer: D