Project Management Professional (PMP) Exam Practice – Question0408

Activity cost estimates are quantitative assessments of the probable costs required to:


A.
Create WBS.
B. complete project work.
C. calculate costs.
D. Develop Project Management Plan.

Correct Answer: B