Project Management Professional (PMP) Exam Practice – Question0412 During project selection, which factor is most important? A. Types of constraints B. Internal business needs C. Budget D. Schedule Show Answer Hide Answer Correct Answer: B Post navigation Project Management Professional (PMP) Exam Practice – Question0411Project Management Professional (PMP) Exam Practice – Question0413