Project Management Professional (PMP) Exam Practice – Question0416

Which of the following are three inputs to the risk register?


A.
Risk register updates, stakeholder register, and quality management plan
B. Communication management plan, enterprise environmental factors, and activity duration estimates
C. Risk management plan, activity cost estimates, and project documents
D. Project scope statement, organizational process assets, and scope baseline

Correct Answer: C