Project Management Professional (PMP) Exam Practice – Question0417 An input of the Create WBS process is: A. requirements documentation. B. scope baseline. C. project charter. D. validated deliverables. Show Answer Hide Answer Correct Answer: A Post navigation Project Management Professional (PMP) Exam Practice – Question0416Project Management Professional (PMP) Exam Practice – Question0418