Project Management Professional (PMP) Exam Practice – Question0421

While preparing the project management plan on a weekly basis, the project manager indicates the intention to provide an issues report to the staff via e-mail. In which part of the plan will this type of information be included?


A.
Communications management plan
B. Human resource plan
C. Quality management plan
D. Procurement management plan

Correct Answer: A