Which tool or technique can a project manager use to select in advance a team member who will be crucial to the task?
A. Acquisition
B. Negotiation
C. Virtual team
D. Pre-assignment
A. Acquisition
B. Negotiation
C. Virtual team
D. Pre-assignment