Project Management Professional (PMP) Exam Practice – Question0422

Which tool or technique can a project manager use to select in advance a team member who will be crucial to the task?


A.
Acquisition
B. Negotiation
C. Virtual team
D. Pre-assignment

Correct Answer: D