Project Management Professional (PMP) Exam Practice – Question0428 Which type of analysis is used to develop the communications management plan? A. Product B. Cost benefit C. Stakeholder D. Research Show Answer Hide Answer Correct Answer: C Post navigation Project Management Professional (PMP) Exam Practice – Question0427Project Management Professional (PMP) Exam Practice – Question0429