What is a deliverable-oriented hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?


A.
Organizational Breakdown Structure (OBS)
B. Work Performance Information
C. Work Package
D. Work Breakdown Structure (WBS)

Correct Answer: D