Project Management Professional (PMP) Exam Practice – Question0445

Which of the following is used to illustrate the connections between work packages or activities and project team members?


A.
Hierarchical-type charts (HTC)
B. Organizational breakdown structure (OBS)
C. Work breakdown structure (WBS)
D. Responsibility assignment matrix (RAM)

Correct Answer: D