Project Management Professional (PMP) Exam Practice – Question0447

For a project to be successful, the project team must do which of the following?


A.
Complete the project in sequential phases.
B. Overlook minor stakeholders.
C. Produce ongoing repetitive products, services, or results.
D. Select the appropriate processes required to meet the project objective.

Correct Answer: D