Project Management Professional (PMP) Exam Practice – Question0452

A project is ready to complete the planning process, and all planning documents have been reviewed and approved by stakeholders. What should the project manager do next?


A.
Conduct a kick-off meeting.
B. Create the schedule baseline.
C. Acquire the resources.
D. Determine the budget.

Correct Answer: A