Project Management Professional (PMP) Exam Practice – Question0454

A major stakeholder is replaced during the planning phase. The new stakeholder has a different view on the projects business needs and wants to immediately include these newly identified business requirements in the scope to avoid any delays.
What should the project manager do next?


A.
Update the project scope statement.
B. Conduct the Perform Integrated Change Control process
C. Update the project charter.
D. Perform project management plan updates.

Correct Answer: B