Project Management Professional (PMP) Exam Practice – Question0455

In the late stages of project planning, a project manager develops a risk response plan with subject matter experts (SMEs) and project team members. The team identifies additional efforts required to mitigate the risk of poor quality in some deliverables.
What should the project manager do next?


A.
Update the project and quality management plans to reflect the added efforts.
B. Conduct a make-or-buy analysis to determine the best option.
C. Document the additional efforts in the organizational process assets.
D. Generate a change request for approval of the added costs associated with added efforts.

Correct Answer: A