A project manager learns there are several unexpected issues in the projects execution. The customer is dissatisfied because the deliverables are taking longer than planned, the costs have increased, and the quality of deliverables is affected.
What process should the project manager have performed with greater emphasis during project planning?


A.
Plan Risk Management
B. Identify Risks
C. Monitor Risks
D. Plan Risk Responses

Correct Answer: D