Project Management Professional (PMP) Exam Practice – Question0458

A project manager joins a project during its initial planning phase. The project involves various local government institutions. While interviewing the project sponsor, the project manager learns of the importance of keeping the security officers of two of these
institutions satisfied, since project development will be affected without their involvement.

What should the project manager use to record and monitor this information?


A.
Responsibility assignment matrix (RAM)
B. Power/interest grid
C. Communication matrix
D. Risk register

Correct Answer: B