Project Management Professional (PMP) Exam Practice – Question0462

While working on a project, the project manager realizes that stakeholders delivery expectations differ from what was initially planned. What should the project manager have done to avoid this?


A.
Created acceptance criteria, an assumptions log, and requirements documentation.
B. Discussed expectations and possible changes with the project sponsor
C. Develop a requirements traceability matrix
D. Maintained a risk register for out-of-scope requirements

Correct Answer: A