Project Management Professional (PMP) Exam Practice – Question0463

After reviewing the project management plan, a project manager notices that some of the resistant team members have become supportive.
Where should the project manager update this information?


A.
Quality management plan
B. Resource management plan
C. Stakeholder engagement plan
D. Communications management plan

Correct Answer: C