Upon approval, a new project manager immediately begins a project. Three months into the project, the project manager identifies numerous obstacles.
What should the project manager have done?


A.
Identified risks
B. Performed a qualitative risk analysis
C. Performed a quantitative risk analysis
D. Planned risk responses

Correct Answer: A