Project Management Professional (PMP) Exam Practice – Question0470

A project manager identifies that three leaders in the organization have three different expectations about what should be implemented in a project. What did the project manager use to identify this?


A.
Stakeholder analysis
B. Deliverables definition
C. Quality variances
D. Project charter development

Correct Answer: A