Project Management Professional (PMP) Exam Practice – Question0471

A performing organization is consulted to implement a supply chain management application for a beverage manufacturing business. During a project meeting with the customer, the performing organization mentions that the predefined budget allocation by the
customer needs to be addressed.

Where did the project manager find this information?


A.
Project exclusions
B. Project assumptions
C. Project deliverables
D. Project constraints

Correct Answer: B