Project Management Professional (PMP) Exam Practice – Question0472

Which risk analysis diagram is used to compare the relative importance and impact of variables that have a high degree of uncertainty to those that are more stable?


A.
Decision tree
B. Tornado
C. Ishikawa
D. Monte Carlo

Correct Answer: B