A project manager joins a project that must comply with a countrys government regulations. The government is providing a six-month grace period before applying financial penalties. To implement this project, a small group of stakeholders will be involved, who
have the legal right to defend their interests and can cause a financial impact on the organization.

What should the project manager do?


A.
Conduct a probability and impact assessment.
B. Allow any issues to be handled by management.
C. Adjust the schedule to include time for handling objections.
D. Create the project management plan and wait to act until issues actually occur.

Correct Answer: A